top of page

Epping Terminal
Epping, ND

This project was a dual site in-house, design-build project that tied the owner’s assets into the Dakota Access pipeline. Ross Group Industrial provided new foundation systems and added launchers and receivers, interconnecting pipe, underground transmission lines, MCC, and a prover building. The project was completed in a fast-tracked 109-day schedule, from conceptual engineering to flowing product.

bottom of page